Projects

Stabilized bank of West Branch. View of river and brown-vegetated bank.
West Branch Delaware River
Delaware County Fairgrounds
  • Completed 2023
  • Location: West Branch Delaware River, Walton
  • Project Cost: $99,427 
  • Project Partners: DCSWCD, NYCDEP and Village of Walton
Project Objective:

The purpose of the project is to protect the Delaware County Fairground and the existing main utility pole that services the Village of Walton.

Project Description:

The streambank was observed to be actively eroding along West Branch Delaware River and posed a significant risk to public infrastructure while also contributing a significant amount of sediment to the West Branch Delaware river. In order to maintain the safety and integrity of the utility and the public, the project consisted of removal of on-site material and placement of rock rip rap with topsoil. The rock was covered with soil to encourage vegetation growth and minimize thermal impacts to the river. Live willow stakes were planted along the embankment.

Coles Clove SL 5.78 bank stabilization project. Image shows black corrugated drainage pipe passing underneath roadway above drains into stream below. Eroding bank around drainage pipe has been rebuilt and enforced with visible large, flat rocks.
Coles Clove SL 5.78 Bank Stabilization
  • Completed October 2022
  • Location: Coles Clove Road, Hamden
  • Project Cost: $34,823 Through The DCSWCD Stream Management Implementation Program Grant
  • Project Partners: DCSWCD, NYCDEP And The Town Of Hamden
Issue that Project is Addressing:
A storm event that occurred in the Town of Hamden between August 13 and August 15, 2018 resulted in streambank erosion at several locations adjacent to town-maintained roads. The project is located approximately 1,450 linear feet downstream of the intersection of Terry Clove Road, Basin Clove Road, and Coles Clove Road. At the SL 5.78 site, the Basin Clove stream has undermined the Coles Clove Road embankment. Hydraulic erosion in the vicinity of a cross culvert outlet has led to left bank erosion immediately adjacent to the roadway. Continued erosion poses risk of immediate embankment failure. The Town of Hamden applied for grant funding through the Stream Management Program.
Project Description:
The project design stream length of 25 feet that included the placement of stacked rock wall along the left streambank and fill will be placed from the top of the rock wall to the edge of the road shoulder. The project goals is to produce the necessary bankfull shear stress within the stream channel required to maintain sediment competence and ensure lateral stability of the streambank.
Cloves Clove SL 4.62 Bank Stabilization project. Image shows view upstream from edge of the roadway toward a newly installed stacked rock wall.
Coles Clove SL 4.62 Bank Stabilization
  • Completed September 2022
  • Location: Intersection of Coles Clove and Basin Clove Roads, Hamden
  • Project Cost: $119,427 through the DCSWCD Stream Management Implementation Program Grant
  • Project Partners: DCSWCD, NYCDEP and Town of Hamden
Issue that Project is Addressing:

A storm event that occurred in the Town of Hamden between August 13 and August 15, 2018 resulted in streambank erosion at several locations adjacent to town-maintained roads. One of these locations, SL 4.62, is located at the Terry Clove Road, Basin Clove Road, and Coles Clove Road intersection. At the SL 4.62 site, the Basin Clove stream has eroded the road shoulder and undermined the roadway embankment. Continued lateral migration and hydraulic erosion at the toe of the roadway embankment threatens the integrity and safety of the town infrastructure. The Town of Hamden applied for grant funding through the Stream Management Program.

Project Goals (and how achieved):

The project design stream length of 125 feet that included the placement of stacked and pinned rock wall along the left streambank and two (2) hardened riffles for grade control. The grade control structures would help maintain water quality by limiting any potential head-cuts from advancing upstream. This design would implement the project goals and objectives established by the Stream Management Program staff, while providing water quality benefits for the New York City Department of Environmental Protection (DEP) and communities that rely on drinking water sources from the West-of-Hudson River Watershed.

View from left bank overlooking Walton's West Brook stream toward existing water main after installation of hardened riffle.
West Brook - Delaware Street Bridge
  • Completed September 2022
  • Location: West Brook Near Sunoco Gas Station, Walton
  • Project Cost: $37,495 Through The DCSWCD Stream Management Implementation Program Grant
  • Project Partners: DCSWCD, NYCDEP And The Village Of Walton
Issue that Project is Addressing:

West Brook is one of the three tributaries flowing through the Village of Walton. Vertical stacked rock walls, urban development and encroachment, and a general lack of floodplain connectivity are common issues along the West Brook stream corridor through the Village. Energy dissipation is minimal and, with lateral migration inhibited, the bed of West Brook has continued to erode. At Site #8, a water main concrete encasement is exposed. Despite the adjacent floodplain enhancement project along the right bank, this crossing is at risk of being damaged or undermined during a future storm event. The Village of Walton applied for grant funding through the Stream Management Program.

Project Goals (and how achieved):

The streambank was observed to be actively eroding along West Branch Delaware River and posed a significant risk to public infrastructure while also contributing a significant amount of sediment to the West Branch Delaware river. In order to maintain the safety and integrity of the utility and the public, the project consisted of removal of on-site material and placement of rock rip rap with topsoil. The rock was covered with soil to encourage vegetation growth and minimize thermal impacts to the river. Live willow stakes were planted along the embankment.

Other Info:

The Village of Walton owns numerous underground utilities that cross three major tributaries of the West Branch Delaware River within the Village limits. At thirteen known locations, the utilities – water, sewer, or both, in close proximity – are threatened by the three tributaries’ continued streambed scour. Previous storm events, including most recently in 2006, resulted in damage to five of the thirteen crossing locations, leading to costly utility repairs, temporary lack of potable water for Village residents, and raw sewage leaks. Potential leaks could contaminate the West Branch and the Cannonsville Reservoir downstream, one of New York City’s unfiltered drinking water supply sources.

Beginning of Walton Village's West Brook stream well bank stabilization project remediation showing large excavator and dump truck reconfiguring streambank soil.
West Brook
Village Well Bank Stabilization
  • Completed September 2022
  • Location: West Brook Near The Village Of Walton’s Well
  • Project Cost: $124,894 Through The DCSWCD Stream Management Implementation Program Grant
  • Project Partners: DCSWCD, NYCDEP And The Village Of Walton
Issue that Project is Addressing:
The streambank was observed to be actively eroding along West Brook and posed a significant risk to the Village of Walton’s drinking water well. In order to maintain the safety and integrity of the utility and eliminate further pollution of the stream from sediment, the Village of Walton applied for grant funding through the Stream Management Program.
Project Goals (and how achieved):
The project consisted of rock rip-rap to address the streambank erosion and two grade control structures. Halting streambed scour at the utility with the grade control structures limits the potential for an advancing head-cut to degrade the West Brook streambed. The rock was covered with soil to encourage vegetation growth and minimize thermal impacts to the stream channel and benching is planned to re-establish the correct balance for this reach.
Downstream view of East Brook after project completion. Mountains in background and green grassy banks on either side of East Brook.
East Brook - Bank Stabilization
  • Completed 2021
  • Location: East Brook, Walton
  • Project Cost: $234,300
  • Project Partners: DCSWCD, NYCDEP, Conservation Reserve Enhancement Program, And The Watershed Agricultural Council
Project Objective:

The purpose of the project is to stabilize the streambank for the property to qualify for the federal Conservation Reserve Enhancement Program (CREP) and the NYC DEP funded Catskill Stream Buffer Initiative (CSBI) on fallow agricultural riparian properties.

Project Description:

The CREP/CSBI pilot program was developed in 2017 by the DCSWCD, the Watershed Agricultural Council, and the NYC Dept. of Environmental Protection. The pilot program was created to merge the federal CREP and the NYC DEP funded CSBI on fallow agricultural riparian properties in Delaware County. CREP/CSBI has planted native vegetation along both the top right and top left banks of East Brook in numerous locations along the East Brook property; however, in order to complete the plantings, the streambank must be restored to a stable reach. The project included stream channel sizing, dimensioning and realignment for 740 linear feet with hardened rock toe on left and right banks near pool locations; 8 grade control structures, 1 hardened riffle, installation of sod mats and willow live stakes. Floodplain bench and multi-stage channel will provide floodplain connection while improving flood-flow and sediment conveyance.

Approximately the same location after construction of floodplain benches along both streambanks and step-pools. The large woody debris has been removed.
Steele Brook Phase II
Streambank Stabilization
  • Steele Brook Subwatershed
  • Completed 2021
  • Project Length: 350′
  • Location: Steele Brook, Village of Delhi
  • Project Partners: DCSWCD, NYCDEP, US Army Corps of Engineers
Project Objective:

The purpose of the project was to repair the streambank along old access road for future projects.

Project Description:
This project was a recommendation in the Village of Delhi Local Flood Analysis Plan.  The purpose of this project will ultimately enhance water quality by stabilizing the eroding right bank and preventing further sediment deposition into Steele Brook. Stream channel sizing, dimensioning and realignment for 350 linear feet with the installation of 5 in-stream steps; floodplain bench to be installed along both sides of the streambank with a hardened rock toe; and re-vegetation of the eroding bank. Tree removal of approximately 82 trees flagged within a 0.51 mile length of Steele Brook. These trees were identified during the 2017 Steele Brook Stream Feature Inventory as posing a significant flood threat to the Village of Delhi. Mobilization of this debris and transport downstream would lead to potential blockage of the undersized bridge within the Village.
Stacked rock wall along the left streambank and floodplain bench on the right.
Steele Brook Phase I 
Streambank Stabilization
  • Steele Brook Subwatershed
  • Completed 2021
  • Project Length: 460′
  • Location: Steele Brook, Delhi
  • Project Partners: DCSWCD, NYCDEP, US Army Corps of Engineers
Project Objective:

The purpose of the project is to repair streambank along old access road for future projects.

Project Description:

This project was a recommendation in the Village of Delhi Local Flood Analysis Plan. The purpose of this project was to reduce lateral stream migration of Steele Brook and the resultant sediment loading from streambank erosion within the project reach. The repair of stream channel sizing, dimensioning and realignment for 460 linear feet with stacked rock wall along the left streambank; floodplain bench; and re-vegetation of the eroding bank. Restore access route at the top of the slope; culvert replacement at two (2) stream crossings along route; and culvert replacement at three (3) drainage locations along access route. Tree removal of approximately 82 trees flagged within a 0.51 mile length of Steele Brook. These trees were identified during the 2017 Steele Brook Stream Feature Inventory as posing a significant flood threat to the Village of Delhi. Mobilization of this debris and transport downstream would lead to potential blockage of the undersized bridge within the Village.

PAST PROJECTS